Fig. 4From: Spreading of performance fluctuations on real-world project networksFor each activity of each project, we report Start Delay (in days) and RH score (at the node level). Data are binned uniformly along the RH dimension to mitigate noise. A trend emerges in all four datasets with higher RH values corresponding to longer delays, i.e., worse performance. As it is particularly evident from DC and PN, a significant contribution to this phenomenon comes for the outliers in the Start Delay distribution, the best-performing activities, that tend to score low in RH. Bin cuts and bin populations for all datasets are reported in Table 3Back to article page